RM36D0EC _57 Power Source / Network _087045 M20C-FKS BATTERY / CHARGING _0418151 GENERATOR A

M20C-FKS BATTERY / CHARGING  GENERATOR  INSTALLATION  


PROCEDURE

Hide 27020 1.INSTALL GENERATOR ASSEMBLY

a.

Install the generator assembly with the bolt and 2 nuts.

Torque:
25 N*m (255 kgf*cm, 18 ft.*lbf)


b.

Install the wire harness clamp bracket to the generator assembly with the bolt.

Torque:
10 N*m (102 kgf*cm, 7 ft.*lbf)


c.

Connect the wire harness to the terminal B with the nut.

Torque:
9.8 N*m (100 kgf*cm, 87 in.*lbf)


d.

Close the terminal cap.


e.

Connect the generator assembly connector.


Hide 5. INITIALIZATION AFTER RECONNECTING BATTERY TERMINAL

HINT:

When disconnecting and reconnecting the battery, there is an automatic learning function that completes learning when the respective system is used.

Click hereGeneral>SETUP>WHEN DISCONNECTING OR RECONNECTING BATTERY TERMINAL>AUTOMATIC LEARNING CHART