The necessary procedures (adjustment, calibration, initialization or registration) that must be performed after parts are removed and installed, or replaced during No. 1 cooler thermistor removal/installation are shown below.
Be sure to read Precaution thoroughly before servicing.
except NR Series Engine:
for NR Series Engine:
After the ignition switch is turned off, there may be a waiting time before disconnecting the negative (-) auxiliary battery terminal.
When the cable is disconnected / reconnected to the auxiliary battery terminal, systems temporarily stop operating. However, each system has a function that completes learning the first time the system is used.
| Effect/Inoperative Function When Necessary Procedures are not Performed | Necessary Procedures | Link |
|---|---|---|
| Front Camera System | Drive the vehicle straight ahead at 15 km/h (9 mph) or more for 1 second or more. | ( 202304,999999,_95,_139716,_0584193,RM1000000029F4C,)
|
87130D
1.REMOVE BLOWER ASSEMBLY
82210K
2.REMOVE AIR CONDITIONING HARNESS ASSEMBLY
87050C
3.REMOVE NO. 1 AIR CONDITIONING RADIATOR DAMPER SERVO SUB-ASSEMBLY
87050E
4.REMOVE NO. 3 AIR CONDITIONING RADIATOR DAMPER SERVO SUB-ASSEMBLY (for 8ZR-FXE)
87128
5.REMOVE HEATER GROMMET
87124B
6.REMOVE HEATER CLAMP
87107A
7.REMOVE HEATER RADIATOR UNIT SUB-ASSEMBLY
88899L
8.REMOVE COOLING UNIT PARTS
88515
9.REMOVE COOLER EXPANSION VALVE
88501
10.REMOVE NO. 1 COOLER EVAPORATOR SUB-ASSEMBLY
88625
11.REMOVE NO. 1 COOLER THERMISTOR
Remove the No. 1 cooler thermistor.